https://newsletter.mw.creamermedia.com
Cleaning|Construction|Crushing|Energy|Engineering|Exploration|Gold|Health|Housing|Infrastructure|Innovation|Mining|PROJECT|Safety|Services|System|Environmental|Infrastructure|Operations
Cleaning|Construction|Crushing|Energy|Engineering|Exploration|Gold|Health|Housing|Infrastructure|Innovation|Mining|PROJECT|Safety|Services|System|Environmental|Infrastructure|Operations
cleaning|construction|crushing|energy|engineering|exploration|gold|health|housing|infrastructure|innovation|mining|project|safety|services|system|environmental|infrastructure|operations

Blackwater gold project, Canada – update

Location map of the Blackwater project

Photo by Artemis Gold

6th September 2024

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

     

Font size: - +

Name of the Project
Blackwater gold project.

Location
Central British Columbia, Canada.

Project Owner/s
Artemis Gold.

Project Description
A feasibility study has shown several positive changes in the approach to the planned development of the Blackwater project, compared with the prefeasibility study (PFS) completed in 2020. 

Phase 1 throughput has been increased by 9%, from 5.5-million tonnes a year in the PFS to six-million tonnes a year in the feasibility study, with a larger crushing circuit providing greater operational throughput upside potential in the early years.

The accelerated Phase 2 involves the expansion to nine-million tonnes a year in Year 5, ramping up to 12-million tonnes a year in Year 6.

The increased production in years 1 to 5 supports a 29 % increase in average gold production over the first five years of operation, to 321 000 oz/y.

The Phase 2 expansion has been simplified and is to be achieved with only minor modifications to the existing Phase 1 crushing, stockpile and ball mill feed system. The second ball mill will operate in series with the Phase 1 mill. The rest of the plant circuits will be duplicated (gravity concentration, leaching, adsorption, elution and cyanide destruction) or expanded. Minor upgrades will be undertaken on some infrastructure to accommodate the increased throughput.

Phase 3 will increase production to 15-million tonnes a year in Year 10, ramping up to 20-million tonnes a year in Year 11.

The increased production in years 1 to 10 results in a 5% increase in the average gold production, to 351 000 oz/y of gold.

The Phase 3 expansion will require a new process line, from primary crushing to cyanide destruction, although a carbon elution circuit will not be needed, as the Phase 1 and 2 units will have sufficient capacity, with the lower ore-grades in Phase 3.  
 
Mining operations are proposed to cease in Year 17, with stockpiled ore rehandled and processed through the process plant in years 18 to 22. The decrease in mine life, from 23 years in the 2020 PFS to 22 years in the feasibility study, is a direct result of the increased throughput rate and production during the first ten years of the mine life in the feasibility study.  

Potential Job Creation
The total workforce at the Blackwater mine, including staff and contractors, surpassed 550 towards the end of December 2023.

Net Present Value/Internal Rate of Return
In the base case, the project has an after-tax net present value, at a 5% discount rate, of C$2.15-billion and an internal rate of return of 32.1%, with a payback of 2.3 years. This compares with an after-tax net present value, at a 5% discount rate, of C$2.25-billion and an internal rate of return of 35%, with a payback of 2.2 years in the PFS.

Capital Expenditure
Between C$730-million and C$750-million.

Planned Start/End Date
Construction is expected to start in the second quarter of 2022, putting the project on track to develop into a new tier-one gold operation in the first quarter of 2024.

Latest Developments
Artemis Gold is complying with an Environmental Assessment Office (EAO) order to vacate the Chu campsite, which has been used to house transmission-line construction workers for the project.

The workers have since relocated to the main camp at the mine, and demobilisation of the Chu camp is well under way.

Artemis has said that the demobilisation process will not impact on the overall schedule or costs of the Blackwater mine construction.

Chu camp was originally an abandoned mining exploration site under the custody of the Ministry of Energy, Mines and Low Carbon Innovation.

According to a spokesperson for Artemis, the company saw an opportunity to support the provincial government by cleaning up the Chu camp while providing housing for its transmission-line workforce, thus minimising environmental, health and safety impacts. 

In March 2024, the Ministry of Energy, Mines and Low Carbon Innovation transferred the permit for the Chu camp location to Blackwater mine, consequently enabling Artemis to operate the camp. Under its agreement with the Ministry, Artemis committed to remediating the Chu camp, which included dismantling old buildings and infrastructure left by the previous owner, at a cost of more than C$200 000.

However, the EAO recently determined that the Chu camp was noncompliant with Artemis’ environmental-assessment certificate, prompting the order to vacate.

Key Contracts, Suppliers and Consultants
Ausenco Engineering Canada, with the support of Knight Piésold; Moose Mountain Technical; Allnorth Consultants; Lorax Environmental Services; ERM Consultants; and JAT MetConsult (feasibility study).

Contact Details for Project Information
Artemis Gold, tel +1 604 558 1107 or email info@artemisgoldinc.com.

Edited by Creamer Media Reporter

Comments

Latest News

A test mine established by the MMP
MMP looks to the future with a new strategy
18th November 2024 By: Sabrina Jardim

Showroom

SABAT
SABAT

From batteries for boats and jet skis, to batteries for cars and quad bikes, SABAT Batteries has positioned itself as the lifestyle battery of...

VISIT SHOWROOM 
SMS group
SMS group

At SMS group, we have made it our mission to create a carbon-neutral and sustainable metals industry.

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Photo of Martin Creamer
On-The-Air (15/11/2024)
15th November 2024 By: Martin Creamer
Magazine round up | 15 November 2024
Magazine round up | 15 November 2024
15th November 2024

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.053 0.229s - 130pq - 2rq
Subscribe Now