Cameco flags 2025 production hit amid McArthur River mine transition delays

29th August 2025

By: Reuters

  

Font size: - +

Canadian uranium supplier Cameco said on Thursday the development delays in transitioning the McArthur River mine in Saskatchewan to new mining areas are expected to impact its 2025 production forecast.

The company cited risks including development delays and the expected timing of ground freezing as the mine transitions into two new mining areas.

Additionally, challenges related to access to skilled labor and the timing of commissioning new customized equipment are also potential risks.

"Production from the McArthur River/Key Lake operation is now anticipated to be between 14-million and 15-million pounds of uranium concentrate (U3O8)," the company said, adding, this production projection was lower than its previous forecast of 18 million pounds.

Cameco also said that it was unable to fully mitigate the impact of delayed development and slower-than-anticipated ground freezing in the first half of this year.

However, strong performance at the Cigar Lake mine may partially offset the deferred McArthur River production, the statement mentioned.

Edited by Reuters

Comments

Showroom

Immersive Technologies
Immersive Technologies

Immersive Technologies is the world's largest, proven and tested supplier of simulator training solutions to the global resources industry.

VISIT SHOWROOM 
AutoX
AutoX

We are dedicated to business excellence and innovation.

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Resources Watch
Resources Watch
27th August 2025

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.045 0.121s - 145pq - 2rq
Subscribe Now