Gamsberg Phase 2 expansion project, South Africa – update
Photo by Vedanta Zinc International
Name of the Project
Gamsberg Phase 2 expansion project.
Location
Namakwa Special Economic Zone, in the Northern Cape, South Africa.
Project Owner/s
Vedanta Zinc International (VZI) subsidiary Black Mountain Mining (BBM).
Project Description
The project will double the capacity of the Gamsberg zinc mine and plant, from four-million tonnes a year to more than eight-million tonnes a year; and include the construction of a four-million-tonne-a-year concentrator, increasing output from 300 000 t/y to 500 000 t/y of metal in concentrate.
The project’s current mineral reserves and resources show a potential life-of-mine of 50 years.
Potential Job Creation
The project is expected to create 2 000 to 2 500 jobs during the construction phase and a further 800 to 1 000 permanent jobs during the peak operations phase.
Net Present Value/Internal Rate of Return
Not stated.
Capital Expenditure
Approved capital expenditure was estimated at $466-million as at June 2024.
Planned Start/End Date
The expansion project was approved in the fourth quarter of 2022. The project is targeted to be completed by the first half of the 2024/25 financial year, with engineering and full ramp-up targeted for the 2025/26 financial year.
Latest Developments
Vedanta has reported in an investor presentation for the first quarter of the 2025 financial year that engineering and procurement on the project are about 100% and 97% completed respectively.
Concrete, and the erection of structural steel and equipment is on track.
Completion is expected by the end of the second half of the 2025 financial year.
Key Contracts, Suppliers and Consultants
Onshore (engineering, procurement and construction partner); TCE (owner’s engineers); M&D (construction partner); WBHO (tailings storage facility); Afriline (external water system); PPE (external power system); and CITIC Heavy Industries (ball and semiautogenous grinding mills).
Contact Details for Project Information
VZI, tel +27 11 685 3960 or email info@vedantaresources.co.za.
Comments
Press Office
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation