Electricity and Energy Minister Dr Kgosientsho Ramokgopa indicates that he is in favour of grid-access rules that ensure as much new capacity is added as quickly as possible regardless of whether that new generation is procured through public or private processes.

The Minister was responding to a question as to whether upcoming Renewable Energy Independent Power Producer Procurement Programme (REIPPPP) bidding rounds could be threatened if the Energy Regulator refused to allow Eskom to reserve grid capacity for such projects.

In a submission to the National Energy Regulator of South Africa (Nersa), Eskom said it was necessary to preserve and reserve grid capacity to protect the REIPPPP from failures similar to what was experienced during REIPPPP Bid Window 6.

During that bid window, no wind projects progressed to the preferred-bidder stage as the grid capacity on which they were premised was allocated to independent power producers proceeding on the back of private power purchase agreements.

Eskom argued that, without protection, public procurement programmes would be incapable of competing with the much more agile private procurement programmes.

Following an extended public-comment period, it was reported by Moneyweb that Nersa’s electricity sub-committee recommended that the Energy Regulator reject Eskom’s application when it met to make a final determination.

Ramokgopa argued that the “problem statement” facing South Africa was the need to rapidly add new capacity to a grid that remained vulnerable to loadshedding despite recent improvements, rather than prioritising the credibility of the public procurement process.

The Minister indicated that he was supportive of an outcome that allowed projects that were ready to proceed.

“We are solving a bigger problem.

“We are not solving for the credibility of the public-procurement process; we are solving an energy-deficit problem.

“So if the private sector is ready, I’m of the opinion that they should be allowed to come on stream,” Ramokgopa explained.

Edited by Martin Zhuwakinyu
Creamer Media Senior Deputy Editor

Comments

Latest News

An image showing the Kloof gold mine
Sibanye-Stillwater secures six health and safety awards
18th November 2024 By: Tasneem Bulbulia

Showroom

Weir Minerals Africa and Middle East
Weir Minerals Africa and Middle East

Weir Minerals Europe, Middle East and Africa is a global supplier of excellent minerals solutions, including pumps, valves, hydrocyclones,...

VISIT SHOWROOM 
Multotec
Multotec

Multotec, recognised industry leaders in metallurgy and process engineering help mining houses across the world process minerals more efficiently,...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Photo of Martin Creamer
On-The-Air (15/11/2024)
15th November 2024 By: Martin Creamer
Magazine round up | 15 November 2024
Magazine round up | 15 November 2024
15th November 2024

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.054 0.201s - 125pq - 2rq
Subscribe Now