https://newsletter.mw.creamermedia.com
Compressor|Construction|Copper|Drilling Equipment|Infrastructure|Installation|Mining|PROJECT|Service|Simulator|System|Testing|Training|Waste|Equipment|Drilling|Infrastructure|Waste
Compressor|Construction|Copper|Drilling Equipment|Infrastructure|Installation|Mining|PROJECT|Service|Simulator|System|Testing|Training|Waste|Equipment|Drilling|Infrastructure|Waste
compressor|construction|copper|drilling-equipment|infrastructure|installation|mining|project|service|simulator|system|testing|training|waste-company|equipment|drilling|infrastructure|waste

Kansanshi mine – S3 expansion project, Zambia – update

Aerial view of the Kansanshi mine

Photo by First Quantum Minerals

21st February 2025

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

     

Font size: - +

Name of the Project
Kansanshi mine – S3 expansion project.

Location
Zambia.

Project Owner/s
Canada-based mining and metals company First Quantum Minerals (FQM).

Project Description
The project has total proven and probable reserves of 842.7-million tonnes grading 0.63% total copper. Total measured and indicated reserves are estimated at 939.6-million tonnes grading 0.67% total copper for a mine life of 24 years.

The S3 expansion is expected to transition the current selective high-grade, medium-scale operation to a medium-grade, larger-scale mining operation that will be more appropriate for the higher proportion of primary, lower-grade sulphide ores at depth.

When completed, the S3 expansion will comprise a standalone 25-million-tonne-a-year processing plant with a new and larger mining fleet, which will increase Kansanshi’s total yearly throughput to 53-million tonnes.

The S3 processing train will include a 28 MW semiautogenous grinding mill and a 22 MW ball mill. The openpit mine will be expanded to increase the supply of sulphide ore from the main pit and extend into the south-east dome deposit.

The expanded mining fleet will use high-end equipment and will include new electric loading and drilling equipment, along with the extension of the current electric trolley assist infrastructure.

In parallel with the expansion of the mine and processing facilities, First Quantum plans to increase the throughput capacity of the Kansanshi smelter from 1.38-million tonnes a year to 1.65-million tonnes a year of concentrate. This will enable the smelter to produce more than 400 000 t/y of copper anode.

Once the expansion is completed, copper production from Kansanshi is expected to average about 250 000 t/y for the remaining life-of-mine to 2044.

Potential Job Creation
The project will add about 800 permanent jobs and a further 1 800 during the construction phase.

Net Present Value/Internal Rate of Return
Not stated.

Capital Expenditure
The total capital expenditure associated with the S3 expansion is expected to be $1.25-billion, which includes $900-million on the S3 plant and mine fleet, and $350-million for prestripping of the south-east dome pit.

Planned Start/End Date
First production from the S3 expansion is expected in 2025.

Latest Developments
FQM has reported that the expansion project is on track for completion by mid-2025, with significant progress made in key construction and commissioning areas. 

By the end of 2024, construction of the process plant had reached 62% completion, with early commissioning work already under way. System configuration of the plant control system was 80% complete, focusing on the cleaner and reagent circuits, as well as functional testing of service areas. 

Operational readiness also stood at 62%, with personnel undergoing training on the process simulator.

Meanwhile, FQM reported in its results for the quarter ended December 31, 2024, that expansion efforts at the Kansanshi smelter are progressing. The new waste heat boiler condenser and fifth train of wet electrostatic precipitators have been successfully commissioned, while installation of the high-pressure oxygen compressor has been completed, with commissioning under way. All major oxygen plant equipment is on-site, and installation is advancing. Acid Plant 5’s civil works are complete, with structural, mechanical, and piping installations ongoing.

Key Contracts, Suppliers and Consultants
None stated.

Contact Details for Project Information
First Quantum Minerals, email info@fqml.com.

Edited by Creamer Media Reporter

Comments

Showroom

Environmental Assurance (Pty) Ltd.
Environmental Assurance (Pty) Ltd.

ENVASS is a customer and solutions-driven environmental consultancy with established divisions, serviced by highly qualified and experienced...

VISIT SHOWROOM 
VEGA Controls SA (Pty) Ltd
VEGA Controls SA (Pty) Ltd

For over 60 years, VEGA has provided industry-leading products for the measurement of level, density, weight and pressure. As the inventor of the...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Magazine round up | 21 February 2025
Magazine round up | 21 February 2025
21st February 2025
BOLSTERING PRESENCE
The project is set to bolster Namibia’s position as one of the world’s leading uranium producers
Uranium mine moving closer to production
21st February 2025 By: Simone Liedtke

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.05 0.182s - 129pq - 2rq
Subscribe Now