https://newsletter.mw.creamermedia.com
Africa|Construction|Consulting|Design|Exploration|Financial|Gold|Infrastructure|Mining|PROJECT|Resources|Roads|Services|Storage|Solutions|Environmental|Infrastructure
Africa|Construction|Consulting|Design|Exploration|Financial|Gold|Infrastructure|Mining|PROJECT|Resources|Roads|Services|Storage|Solutions|Environmental|Infrastructure
africa|construction|consulting-company|design|exploration|financial|gold|infrastructure|mining|project|resources|roads|services|storage|solutions|environmental|infrastructure

Kobada gold project, Mali – update

Location map of the Kobada gold project

Photo by Toubani Resources

17th October 2025

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

     

Font size: - +

Name of the Project
Kobada gold project.

Location
Southern Mali.

Project Owner/s
Africa-focused gold developer Toubani Resources.

Project Description
A definitive feasibility study (DFS) completed in October 2024 has confirmed Kobada as a significant gold development asset underpinned by its large-scale, free-dig and open-pittable oxide resource.

The ore reserve estimate is 53.8-million tonnes at 0.90 g/t for 1.56-million ounces of gold.

The DFS proposes average production of 162 000 oz/y over the current 9.2-year life-of-mine for total gold production of 1.49-million ounces of gold.

Potential Job Creation
Not stated.

Net Present Value/Internal Rate of Return
The project has a pretax net present value, at an 8% discount rate, of $870-million and an internal rate of return of 72%, with a payback of 1.25 years.

Capital Expenditure
The October 2024 DFS estimates total initial development capital of $216-million.

Planned Start/End Date
First gold production is targeted for the third quarter of 2027. 

Latest Developments
Toubani Resources announced a "company-defining" A$395-million funding package on October 10 to fully finance the construction of its flagship Kobada project.

The package comprises a $160-million (A$242-million) gold stream agreement with major shareholder Eagle Eye Asset Holdings (EEA), an additional A$26-million through the accelerated exercise of existing EEA options, and a A$125-million multitranche equity placement to institutional, sophisticated and professional investors at A$0.40 a share.

Toubani retains flexibility to draw down all, part or none of the facility, depending on progress with an alternative senior debt process under way.

The A$125-million placement will be completed in three tranches, including A$45-million from EEA (subject to Foreign Investment Review Board and shareholder approval). The placement price represents a 5.9% discount to Toubani’s last traded price of A$0.425.

EEA will exercise 78-million existing options at A$0.336, adding A$26-million in funds and increasing its shareholding to about 35%.

Funds will be used to cover Kobada’s $216-million development capital requirements, including $60-million for plant construction, $21-million in owner’s project costs and community initiatives, and $43-million for non-process infrastructure such as the tailings storage facility and roads. Additional allocations include $13-million for exploration and growth, $45-million for corporate and working capital, and $3-million for transaction costs.

The funding enables Toubani to progress towards a final investment decision in 2025, with early commitments for long-lead items expected in the near term. The funding follows the positive results the DFS.

MD Phil Russo has said the transaction has positioned Toubani to become the next significant gold producer in West Africa.
EEA will provide $160-million in exchange for 11.1% of gold production at a price equal to 20% of the prevailing spot gold price. Toubani retains flexibility to draw down all, part or none of the facility, depending on progress with an alternative senior debt process under way.

The A$125-million placement will be completed in three tranches, including A$45-million from EEA (subject to Foreign Investment Review Board and shareholder approval). The placement price represents a 5.9% discount to Toubani’s last traded price of A$0.425.

EEA will exercise 78-million existing options at A$0.336, adding A$26-million in funds and increasing its shareholding to about 35%.

Funds will be used to cover Kobada’s $216-million development capital requirements, including $60-million for plant construction, $21-million in owner’s project costs and community initiatives, and $43-million for non-process infrastructure such as the tailings storage facility and roads. Additional allocations include $13-million for exploration and growth, $45-million for corporate and working capital, and $3-million for transaction costs.

Key Contracts, Suppliers and Consultants
Minxcon Group South Africa (mineral resource estimate); DRA Americas (mining and mineral reserves); Maelgwyn Mineral Services (metallurgical testwork); ABS-Africa (environmental and social studies); Epoch Resources (tailings storage facility); SENET (processing plant and infrastructure, including economic valuation and report compilation); Knight Piésold (DFS – tailings dam design and costing); Global Commodity Solutions (DFS – geology and exploration); Entech (DFS – mineral resources); Oreology (DFS – pit optimisations, mine design and mine scheduling); Minero Consulting (DFS – mining operating and capital cost estimation, and ore reserves); Lycopodium (DFS – metallurgical testwork review, process plant design, process plant operating and capital cost estimation); ABS Africa (DFS – environmental and social impact); Anandarasa Advisory (DFS – financial modelling); and Cantilever Future Solutions (DFS – study management and environmental, social and governance oversight); and Endeavour Financial (financial adviser).

Contact Details for Project Information
Toubani Resources, email info@africangoldgroup.com.
 

Edited by Creamer Media Reporter

Article Enquiry

Email Article

Save Article

To advertise email advertising@creamermedia.co.za or click here

Comments

Showroom

AutoX
AutoX

We are dedicated to business excellence and innovation.

VISIT SHOWROOM 
Bell Equipment
Bell Equipment

As one of South Africa's leading manufacturers, Bell Equipment distributes and exports its wide range of heavy equipment globally to mining,...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Resources Watch
Resources Watch
15th October 2025

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.238 0.37s - 130pq - 2rq
Subscribe Now