Los Azules feasibility study a blueprint for future copper mining, says McEwen
Dual-listed McEwen Copper has reported a positive feasibility study for its 100%-owned Los Azules copper project, in Argentina, confirming a long-life, low-cost operation producing high-purity copper cathodes with strong economic returns and leading sustainability performance.
The study estimates an after-tax net present value of $2.9-billion at an 8% discount rate and an internal rate of return of 19.8%, with a payback period of 3.9 years on an initial capital investment of $3.17-billion.
Average production over the first five years is projected at about 204 800 t/y of copper cathode, with life-of-mine production averaging 148 200 t/y over 21 years.
C1 cash costs are estimated at $1.71/lb and all-in sustaining costs at $2.11/lb. Proven and probable reserves total 10.2-billion pounds of copper.
Designed around an on-site leach and solvent extraction and electrowinning (SX/EW) process, Los Azules will produce 99.99% copper cathodes without the need for a smelter. The project is expected to achieve a 72% lower mine-to-metal carbon intensity than the industry average, use 74% less water than conventional milling, and operate on 100% renewable power from wind, hydro and solar sources. McEwen Copper is targeting carbon neutrality (scopes 1 and 2) by 2038.
“The Los Azules feasibility study is more than a technical milestone – it is a blueprint for the future of copper mining,” said McEwen chairperson and chief owner Rob McEwen. “We have delivered a plan for a long-life asset that will play a role in the world’s clean-energy transition.”
VP and Los Azules GM Michael Meding added that the company aimed to create “Argentina’s first regenerative copper mine – a model for responsible and innovative mining".
Project risk has been further reduced through a collaboration agreement with the International Finance Corporation, which may lead debt financing, and through preliminary financing proposals from Tier-1 suppliers such as Komatsu and Sandvik, as well as YPF Luz and European export credit agencies. Indicative proposals could support over $1.1-billion in equipment and infrastructure financing.
Construction is targeted for 2026, with SX/EW startup in 2029 and first copper in 2030.
Comments
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation