https://newsletter.mw.creamermedia.com
Construction|Contractor|Design|Engineering|Mining|Modular|Power|PROJECT|Road|Products
Construction|Contractor|Design|Engineering|Mining|Modular|Power|PROJECT|Road|Products
construction|contractor|design|engineering|mining|modular|power|project|road|products

Mahenge graphite project, Tanzania – update

Image of graphite rock

3rd October 2025

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

     

Font size: - +

Name of the Project
Mahenge graphite project.

Location
Ulanga district of the Morogoro region, Tanzania.

Project Owner/s
Australian mining company Black Rock Mining.

Project Description
Mahenge will be an openpit mining operation, based on mining the Ulanzi and Cascade deposits.

An independent review of the front-end engineering design (FEED) and an enhanced definitive feasibility study (eDFS) has confirmed the Tier 1-scale Mahenge project as robust, with attractive returns.

The project will use contract mining as proposed in the eDFS instead of owner operator mining.

Mahenge ore will be processed over the life-of-mine (LoM) using a four-stage approach where four process plants will be built sequentially in a modular format.

Processing throughput will initially be one-million tonnes a year when the Module 1 process plant is commissioned, increasing to two-million tonnes a year when Module 2 is commissioned, to three-million tonnes a year when Module 3 is commissioned and to four-million tonnes a year with the completion of Module 4.

The four stages will be developed over the initial years of the mine, with the current mine schedule indicating an LoM of 26 years, after which the current defined deposits will be depleted.

The Module 1 and 2 process plants will process ore from the Ulanzi deposit, while the Module 3 and 4 process plants will process ore from the Cascade and Epanko deposits.

The Module 1 process plant will be fed run-of-mine ore at an average grade of 8.24% total graphitic carbon and will recover an estimated 93% of this graphite to produce about 89 000 t/y of graphite products over the first 20 full years of production.

Potential Job Creation
Not stated.

Net Present Value/Internal Rate of Return
The project has an after-tax net present value, at a 10% nominal rate, of $1.38-billion and an internal rate of return 36%, with a payback of 3.8 years.

Capital Expenditure
Based on the FEED work, the updated capital cost estimate for the development of Module 1 is $182-million, including a contingency allowance of $22-million. Module 2 is estimated at $107-million. The updated capital expenditure for modules 3 and 4 is estimated at $117-million and $104-million respectively.

Planned Start/End Date
Black Rock Mining is targeting first production in 2024.

Latest Developments
Black Rock Mining will start early works after raising A$10-million in a recent equity placement.

The programme, which will start in November, is aimed at positioning the company for a rapid ramp-up of construction once a final investment decision (FID) is made. A formal groundbreaking ceremony is planned for October 9.

Early works will cover site-access road improvements, plant site earthworks and survey work for the high-voltage transmission line from Ifakara to Mahenge. Compensation payments for affected communities along the access road corridor will also be finalised.
Black Rock has received A$4.5-million from the first tranche of the placement, with the second tranche subject to shareholder approval at a meeting scheduled for October 17.

CEO John de Vries has said that shareholder support has enabled the company to take the step forward.

De Vries has further noted that the early works milestone follows a string of key developments over the past 18 months, including offtake agreements, the appointment of Tanzanian contractor Taifa, equity support from Posco International, the resolution of tax issues, expanded debt facilities and power supply agreements with Tanesco.

Key Contracts, Suppliers and Consultants
Taifa (contractor). 

Contact Details for Project Information
Black Rock Mining, tel +61 8 9320 7550 or email info@blackrockmining.com.au.

Edited by Creamer Media Reporter

Article Enquiry

Email Article

Save Article

To advertise email advertising@creamermedia.co.za or click here

Comments

Showroom

Avlock International
Avlock International

Avlock International is a leading manufacturer and distributor of Specialized Fastening Systems.

VISIT SHOWROOM 
Alcohol Breathalysers
Alcohol Breathalysers

Supplier & Distributor of the Widest Range of Accurate & Easy-to-Use Alcohol Breathalysers

VISIT SHOWROOM 

Latest Multimedia

sponsored by

This week: Africa must collaborate to protect the planet; Engen showcases digital innovation, long-term commitment to coal sector at Coal Africa 2025 and, Pilot Crushtec demonstrates innovation, sustainability in crushing solutions at Coal Africa 2025
Resources Watch
22nd October 2025

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.145 0.296s - 128pq - 2rq
Subscribe Now