Rebecca-Roe gold project, Australia

Image of gold nuggets

14th March 2025

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

     

Font size: - +

Name of the Project
Rebecca-Roe gold project.

Location
Western Australia.

Project Owner/s
Gold producer Ramelius Resources.

Project Description
The project will create a new mining hub in an underexplored mining region, which Ramelius plans to take advantage of with its proven hub-and-spoke model.

The mining operations will use openpit and underground mining methods. Rebecca will use an openpit method while Roe will use openpit and underground mining methods.
Gold production will average 130 000 oz/y over the nine-year life-of-mine, with a production target of 1.1-million ounces of contained gold, based predominately on measured and indicated portions of the mineral resource, with 54 000 oz drawn from inferred categories.

The processing circuit will process the Rebecca-Roe deposit at a throughput rate of three-million tonnes a year.

The tailings storage facility will comprise a two-cell paddock storage formed by multizoned earthfill embankments. The facility is designed to store 30-million tonnes of tailings at an average rate of three-million tonnes a year, with capacity to contain all supernatant and runoff from rainfall and storm events.

Potential Job Creation
Not stated.

Net Present Value/Internal Rate of Return
The project has a pretax net present value, at a 5% discount rate, of A$448-million at a gold price of A$3 500/oz. Pay back is estimated at four years.

Capital Expenditure
Total capital costs are estimated at A$190-million.

Planned Start/End Date
Mining is planned to start in September 2026 upon the receipt of the Environmental Protection Act Part V, targeted for June 2026, with plant construction to start in 2026/2027.

Production is planned to start in July 2027.

Latest Developments
The Ramelius board approved the start of a definitive feasibility study (DFS) in December 2024. A final investment decision (FID) is expected in July 2025.

The DFS will focus on progressing environmental permitting processes (Rebecca: Part V and Roe: Part IV); completing geotechnical and hydrology work on Roe underground to bring into ore reserves; refining mine designs and site layouts, as well as capital and operating costs; and exploration to bring additional ounces into the mine plan.

Key Contracts, Suppliers and Consultants
No information provided.

Contact Details for Project Information
Ramelius Resources, tel +61 8 9202 1127.
 

Edited by Martin Zhuwakinyu
Creamer Media Senior Deputy Editor

Comments

Latest Multimedia

Photo of Martin Creamer
On-The-Air (14/03/2025)
Updated 2 hours 12 minutes ago By: Martin Creamer

Showroom

Hanna Instruments (Pty) Ltd
Hanna Instruments (Pty) Ltd

We supply customers with practical affordable solutions for their testing needs. Our products include benchtop, portable, in-line process control...

VISIT SHOWROOM 
The Southern African Institute of Mining and Metallurgy
The Southern African Institute of Mining and Metallurgy

The SAIMM started as a learned society in 1894 after the invention of the cyanide process that saved the South African gold mining industry of the...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Magazine round up | 14 March 2025
Magazine round up | 14 March 2025
14th March 2025

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:5.807 5.943s - 129pq - 2rq
Subscribe Now