PERTH (miningweekly.com) – The construction of the Thunderbird mineral sands project, in Western Australia, will be completed within the A$484-million budget, ASX-listed Sheffield Resources said on Tuesday.
Construction is over 75% complete and first delivery of mineral sands product remains on track for the first quarter of 2024.
“Thunderbird construction is advancing at a rapid pace, and we are extremely pleased by the progress made by the Kimberley Mineral Sands (KMS) team. We remain on schedule for commissioning later this year,” said Sheffield executive chairperson Bruce Griffin.
“Our forecast pre-production activities now include anticipated changes to operational mobilisation and scheduling to reduce startup risk, resulting in an anticipated cost increase. It is pleasing to note that KMS has continued to manage the capital expenditures in line with final investment decision estimates despite the inflationary environment. KMS remains extremely well positioned to complete the project comfortably within the current available funding of A$484-million.”
KMS has estimated the total direct expenditures through to commencement of operations to be A$407-million. After allowance for project financing costs, A$54-million of remaining contingency and working capital provisions are available, with a total funding requirement of A$484-million.
The two-stage Thunderbird development pathway sees the initial Stage 1 mining and processing feed rate forecast at 1 085 t/h at the wet concentrate plant (WCP), with Stage 2 doubling the WCP feed rate to 2 170 t/h targeted during Year 5 of operations.
Stage 1 and 2 of operations is estimated to produce 1.4-million tonne a year of zircon and ilmenite concentrates over an estimated 36 year life-of-mine.
Comments
Press Office
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation