https://newsletter.mw.creamermedia.com
Construction|Crushing|Efficiency|Installation|Mining|Modular|PROJECT|Project Management|Resources|Screen|Water|Products|Drilling|Infrastructure
Construction|Crushing|Efficiency|Installation|Mining|Modular|PROJECT|Project Management|Resources|Screen|Water|Products|Drilling|Infrastructure
construction|crushing|efficiency|installation|mining|modular|project|project-management|resources|screen|water|products|drilling|infrastructure

Uis tin mine Phase 1 expansion project, Namibia – update

Image of the Uis tin mine, in Namibia

15th October 2021

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

     

Font size: - +

Name of the Project
Uis tin mine Phase 1 expansion project.

Location
Namibia.

Project Owner/s
Tin mining company AfriTin Mining.

Project Description
A definitive feasibility study (DFS) has confirmed the feasibility of expanding the current Phase 1 processing plant, resulting in a 67% increase in tin concentrate production from 720 t/y to 1 200 t/y.

The DFS proposes enhancements to the current processing plant, which will result in a modular expansion of the existing crushing circuit to increase ore throughput by 50%. It also proposes the upgrade of the existing concentrator circuit to accommodate the increased crushed ore feed tonnage and increase the projected overall tin recovery target from the current 60% to 64%.

The detailed upgrades include:

• the addition of a crusher and screen between the primary jaw crusher and the fines crushing section;

• the addition of a buffer stockpile between the crushing and concentrating sections;

• the increase of the water rejection capacity in the dense-medium separation (DMS) 1 section;

• combining the dense-medium circuits of DMS 2 and DMS 3 to improve operability and stability;

• converting the DMS 2 floats recrush circuit into a closed circuit by adding a classification screen;

• additional spirals to reprocess middlings; and

• the relocation of product handling infrastructure and the installation of an additional shaking table for improved processing capacity. The existing shaking tables will be replaced with Holman tables for higher separation efficiency.

The DFS is based on a tin-only basis and currently excludes tantalum and lithium concentrate as potential by-products – these commodities are being investigated by AfriTin’s metallurgical testwork programme.

The Uis mine has proven and probable reserves of 15.61-million tonnes grading 0.14% tin for 21 536 t of contained metal.

Potential Job Creation
The project will be complemented by the appoint­ment of a skilled and experienced project management and construction management team to reduce implementation time and limit project implementation risks.

Net Present Value/Internal Rate of Return
The project has a net present value of $12.1-million and an internal rate of return of 54%, with a payback of 2.4 years.

Capital Expenditure
The project is estimated at $5.7-million.

Planned Start/End Date
The company aims to complete the expansion by the second quarter of 2022.

Latest Developments
AfriTin Mining has reported drill results for a final five holes drilled at the Uis mine, which demonstrate continuity of the V1/V2 pegmatite mineralisation at depth.

The highest combined metal (tin, lithium and tantalum) content intersection from the drilling contained 0.17% tin, 61 parts per million tantalum and 1.33% lithium oxide over a 51 m intersection at a depth of between 201 m and 252 m.

The drill hole intersections demonstrate the continuity of mineralisation and a potential upgrade to resources at depth, which support the company’s lithium and tantalum by-product initiatives.

AfriTin will initiate another drilling programme in the coming weeks to align the lithium and tantalum resource confidence intervals with the confidence for tin in the current mineral resource estimate.

Key Contracts, Suppliers and Consultants
Minxcon (DFS).

Contact Details for Project Information
AfriTin Mining, tel +27 11 268 6555.

Edited by Creamer Media Reporter

Comments

Showroom

SMS group
SMS group

At SMS group, we have made it our mission to create a carbon-neutral and sustainable metals industry.

VISIT SHOWROOM 
Alcohol Breathalysers
Alcohol Breathalysers

Supplier & Distributor of the Widest Range of Accurate & Easy-to-Use Alcohol Breathalysers

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Photo of Martin Creamer
On-The-Air (15/11/2024)
15th November 2024 By: Martin Creamer
Magazine round up | 15 November 2024
Magazine round up | 15 November 2024
15th November 2024

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:7.357 7.5s - 129pq - 2rq
Subscribe Now