https://newsletter.mw.creamermedia.com
Construction|Design|Gold|Mining|Power|PROJECT|Waste|Waste|Operations
Construction|Design|Gold|Mining|Power|PROJECT|Waste|Waste|Operations
construction|design|gold|mining|power|project|waste-company|waste|operations

Valentine gold project, Canada

Aerial photograph of the Valentine gold project

Photo by Marathon Gold

3rd March 2023

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

     

Font size: - +

Name of the Project
Valentine gold project.

Location
Central region of Newfoundland and Labrador, in Canada.

Project Owner/s
Marathon Gold.

Project Description
An updated feasibility study has presented, for the first time, a three-pit mine plan for the Valentine project, based on the Marathon, Leprechaun and Berry deposits, with increased mineral reserves, an extended mine life and a higher gold production profile.

The study pro­poses the concurrent openpit mining of the deposits.

Average production is estimated at 195 000 oz/y, over 14.3 years. Other aspects of the mine design, like the site layout, basic mill flowsheet, mill expansion strategy, thickened tailings deposition strategy, 400-person camp, and low-cost site power through the NL Hydro power grid, remain as previously conceived in the April 2021 feasibility study.

Potential Job Creation
There will be full time direct employment of 405 persons during peak construction and 522 during operations.

Net Present Value/Internal Rate of Return
The project has an after-tax net present value, at a 5% discount rate, of $648-million and an internal rate of return of 225%, with a payback of 2.8 years.

Capital Expenditure
The project’s cost to complete as at October 31, 2022, was C$463-million.

Planned Start/End Date
First gold is scheduled for January 2025. Pre­stripping of waste material at the Leprechaun deposit started in October 2022 and mining will extend to 2036. Marathon will be mined between 2023 and 2037. Mining at Berry is scheduled to start in the second quarter of 2025, subject to the receipt of all regulatory approvals, and be completed in 2033. The pit will be used for waste rock and tailings disposal starting in 2034.

Latest Developments
Marathon already has federal and provincial approval to mine at the Leprechaun and Marathon deposits – with early construction work having already started – and is working towards including the Berry deposit.

Key Contracts, Suppliers and Consultants
None stated.

Contact Details for Project Information
Marathon Gold manager, investor relations Amanda Mallough, tel +1 416 855 8202 or email amallough@marathon-gold.com.

Edited by Martin Zhuwakinyu
Creamer Media Senior Deputy Editor

Comments

Showroom

The Southern African Institute of Mining and Metallurgy
The Southern African Institute of Mining and Metallurgy

The SAIMM started as a learned society in 1894 after the invention of the cyanide process that saved the South African gold mining industry of the...

VISIT SHOWROOM 
John Ratcliffe
John Ratcliffe

At John Ratcliffe, we are aftermarket specialists for heavy-duty on and off-road vehicles. We engineer and retrofit advanced safety systems, engine...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Photo of Martin Creamer
On-The-Air (14/03/2025)
14th March 2025 By: Martin Creamer
Magazine round up | 14 March 2025
Magazine round up | 14 March 2025
14th March 2025

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.173 0.304s - 129pq - 2rq
Subscribe Now