15-Mile processing hub, Canada

Image of a bar of gold

Photo by ©Bloomberg

8th August 2025

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

     

Font size: - +

Name of the Project
15-Mile processing hub.

Location
Nova Scotia, Canada.

Project Owner/s
Australia headquartered St Barbara.

Project Description
St Barbara announced the results of the concept study for the integration of the project with a 15-Mile processing hub in May 2025.

St Barbara plans to consolidate operations in Nova Scotia, around a centralised processing hub at 15-Mile, counting on a capital-efficient redesign to deliver more than 1.2-million ounces of gold, with reduced environmental disturbance and stable output of more than 100 000 oz/y.

The concept study confirms that the optimal development approach is for the construction of a three-million-tonne-a-year processing plant, relocated from St Barbara’s Touquoy operations, at 15-Mile, with the addition of a new 5.5 MW ball mill to replace the existing 3.5 MW ball mill and one additional leach tank.

The concept study proposes mining all openpits across 15-Mile, and St Barbara’s Beaver dam and Cochrane Hill deposits using conventional drill, blast, load and haul. 

There are four openpits at 15-Mile – Egerton-Maclean, Plenty, Hudson and 149. 

Beaver Dam and Cochrane Hill each have only one openpit. Ore will be sourced from only 15-Mile until Year 4, when Beaver Dam ore mining and haulage starts. 

Cochrane Hill mining and haulage will start in Year 6.

Mill feed from the St Barbara’s Beaver dam and Cochrane Hill projects will be transported by road to the processing hub starting during the project’s fourth and sixth operating years respectively.

Estimated average gold production of about 106 000 oz/y is expected over the project’s 11-year mine life.

Potential Job Creation
Not stated.

Net Present Value/Internal Rate of Return
The concept study estimates a pretax net present value, at a 5% discount rate, of C$1.4-billion and an internal rate of return of 95%, with a payback on initial capital of one year.

Capital Expenditure
C$251-million.

Planned Start/End Date
Not stated.

Latest Developments
St Barbara expects to complete a prefeasibility study by the March quarter of 2026.

Key Contracts, Suppliers and Consultants
Ausenco Engineering Canada (concept study) and Moose Mountain Technical Services (mine design study).

Contact Details for Project Information
St Barbara, tel +61 8 9476 5555 or email info@stbarbara.com.au.

Edited by Martin Zhuwakinyu
Creamer Media Senior Deputy Editor

Comments

Showroom

WearCheck
WearCheck

Leading condition monitoring specialists, WearCheck, help boost machinery lifespan and reduce catastrophic component failure through the scientific...

VISIT SHOWROOM 
SABAT
SABAT

From batteries for boats and jet skis, to batteries for cars and quad bikes, SABAT Batteries has positioned itself as the lifestyle battery of...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Resources Watch
Resources Watch
6th August 2025

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.367 0.506s - 129pq - 2rq
Subscribe Now