Argonaut appeals La Colorada explosives suspension, reports hearing delay

17th May 2018

By: Henry Lazenby

Creamer Media Deputy Editor: North America

     

Font size: - +

VANCOUVER (miningweekly.com) – The TSX-listed equity of gold producer Argonaut Gold traded lower on Thursday after it announced that it has appealed an April Mexican court decision that suspended its explosives permit for the La Colorada mine.

The company has appealed the original Judiciary Court decision to temporarily suspend the explosives permit to the Collegiate Tribunal, which is an arm of the State Supreme Court that is tasked with overseeing the Judiciary Court. 

This appeal requests the Collegiate Tribunal to reinstate the explosives permit so that the company can blast material while the judiciary legal process continues.

Meanwhile, a judicial court hearing regarding the explosives permit has been rescheduled, this time to June 4. Four individuals have brought a legal suit against the Secretary of National Defence and the Municipality of La Colorada, based on assertions that the explosive permit should not have been granted.

The company is pursuing both the Judiciary legal process and the Collegiate Tribunal appeal process and anticipates it has material sufficient to allow these processes to run their course.

With free-dig material in the pit and ore stockpiles, the company estimates it has sufficient ore to continue operations until the end of July at its budgeted crushing throughput level of 12 000 t/d. The company has reviewed its 2018 consolidated production forecast and, under the assumption the explosive permit is reinstated by August 1, it has guided for production of between 165 000 oz and 180 000 oz of gold equivalent.

The company’s first-quarter profit rose 61% to $7.9-million, on the back of higher metals sales and realised prices, which together with 10% lower all-in sustaining costs being down 10%, benefitted the top line.

Early in the afternoon trading session, Argonaut’s TSX-listed equity traded at C$2.46 a share, down 3.91% for the day.

Edited by Creamer Media Reporter

Article Enquiry

Email Article

Save Article

Feedback

To advertise email advertising@creamermedia.co.za or click here

Showroom

ATI Systems
ATI Systems

ATI systems comprises five divisions: electrical assemblies, drives and controls, feedback sensors, enclosures, and strip guiding.

VISIT SHOWROOM 
Essentra Components
Essentra Components

We are responsible manufacturers of essential components. Manufacturing 80 million parts a week, we have over 1 billion parts in stock.

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Ricards Bay Coal terminal chairperson Nosipho Damasane.
Transnet, Richards Bay Coal Terminal to establish project office
27th January 2026 By: Martin Creamer

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.136 0.222s - 143pq - 2rq
Subscribe Now