https://newsletter.mw.creamermedia.com
Business|Construction|Design|Engineering|Exploration|Flow|Gold|Mining|Power|Storage|Systems|Water|Equipment|Flow
Business|Construction|Design|Engineering|Exploration|Flow|Gold|Mining|Power|Storage|Systems|Water|Equipment|Flow
business|construction|design|engineering|exploration|flow-company|gold|mining|power|storage|systems|water|equipment|flow-industry-term

Artemis Gold lifts Blackwater capacity, orders long-lead equipment for Phase 2

An April 2025 view of the Blackwater site in British Columbia.

An April 2025 view of the Blackwater site in British Columbia.

18th September 2025

By: Mariaan Webb

Creamer Media Senior Deputy Editor Online

     

Font size: - +

Artemis Gold has approved plans to increase throughput at its Blackwater mine in British Columbia, announcing a 33% expansion of the Phase 1 processing plant and placing orders for key equipment ahead of a Phase 2 expansion.

The company said this week that Phase 1 capacity would rise from 6-million tonnes a year to 8-million tonnes a year by the fourth quarter of 2026. Known as Phase 1A, the expansion will cost between C$100-million and C$110-million, equating to a capital intensity of C$50/t to C$55/t – one of the lowest in the industry.

CEO Dale Andres told delegates at the Mining Forum Americas conference, in Colorado Springs, that the upgrade marked “the next step in a transformational journey” for the company. “Blackwater is a Tier 1 asset in a Tier 1 jurisdiction. We have eight-million ounces of gold in reserve, very low all-in sustaining costs (AISC) and we’re generating strong cash flow. We are proud of delivering Blackwater in an industry-leading 22 months, but we are just getting started,” he said.

Construction on Phase 1A has already started, with earthworks under way and a vertical mill ordered to provide additional grinding capacity. Enhancements will also include an expanded leach circuit, upgraded oxygen and elution systems, reagent delivery optimisation, additional water storage ponds and a crushed ore stockpile cover.

Andres said Phase 1A would de-risk the business and provide additional cash flow to help fund the larger Phase 2 expansion, which the board is expected to consider before year-end. To accelerate that timeline, Artemis has ordered an 18 MW semi-autogenous grinding mill and an 18 MW ball mill, the latter already fully fabricated.

“On completion, Phase 2 has the potential to increase production to over 500 000 gold equivalent ounces per year,” Andres said. “If we sanction this in the fourth quarter of 2025, I would say a nominal two-year build. We are still finalising the front-end engineering design, but stay tuned – we are two to three months away from announcing.”

Artemis reiterated its 2025 production guidance of 190 000 oz to 230 000 oz of gold at an AISC of $670/oz to $770/oz. With strong cash flows, a low strip ratio and cheap hydroelectric power from the British Columbia grid, Andres said the company was positioned in the lowest decile of global gold producers.

“2025 is already a transformative year, but it is only the beginning,” he told the forum. “Phase 1A is a capital-efficient step change, Phase 2 will be transformational, and beyond that we have a tremendous land package with more than 30 regional exploration targets that will support growth for the next decade.”

Edited by Creamer Media Reporter

Article Enquiry

Email Article

Save Article

Feedback

To advertise email advertising@creamermedia.co.za or click here

Projects

Showroom

Monitor Distributors
Monitor Distributors

We at Hawk High Pressure Pumps specialise in industrial pumps and pumping systems. Our high pressure washing equipment is locally manufactured and...

VISIT SHOWROOM 
Invincible Valves
Invincible Valves

Established in 1982, Invincible Valves is a medium-sized enterprise in Germiston, serving global and local markets.

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Resources Watch
Resources Watch
26th November 2025

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.146 0.227s - 145pq - 2rq
Subscribe Now