Burnstone gold project, South Africa – update

Image of gold bars

Photo by ©Bloomberg

17th May 2024

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

     

Font size: - +

Name of the Project
Burnstone gold project.

Location
Balfour area, in Mpumalanga, South Africa.

Project Owner/s
Sibanye-Stillwater.

Project Description
The Burnstone project is a low-cost, extensively predeveloped gold asset, which was previously operated under Great Basin Gold.

Existing infrastructure includes a functional metallurgical facility; an established tailings storage facility; an equipped and functional decline shaft and trackless decline; surface infrastructure, such as offices, workshops and compressors; and extensive underground development and infrastructure.

The relatively shallow underground mining operation will mine the Kimberley reef to an average depth of about 550 m below surface (deepest 1.05 km).

The life-of-mine (LoM) is estimated at 22 years.

The project will produce about 138 000 oz/y of gold at steady state with a LoM to 2044.

Potential Job Creation
At the end of the first half of 2023, there were 740 people on site.

Net Present Value/Internal Rate of Return
The last optimised project evaluation showed a 20% internal rate of return and a net present value of R1.3-billion at a gold price of R800 000/kg (2022 real terms).

Capital Expenditure
Total project capital of R2.8-billion (from 2021 onwards) and preproduction capital of R1.5-billion.

In Sibanye’s annual results for the year ended March 31, 2024, Sibanye reported that it had spent about R2.7-billion on Burnstone. For 2024, planned project capital for Burnstone is R390-million, which pertains to critical work that will continue to ensure a successful ramp-up after the project's delay.

Planned Start/End Date
The timeline to steady-state production has been delayed from December 2025 to August 2026.

Latest Developments
Capital investment has been deferred, with stoping and development activities ceasing, apart from the main shaft decline development.

All construction has also been suspended, except the completion of the surface conveyors, including the new waste conveyor, with planned completion at the end of May 2024, and the support of Settler No 1 and Clearwater Dam No 1 and 2, with planned completion at the end of June 2024.

In the quarter ended March 31, 2024, R210-million was spent on the project.

The project, following the deferral of capital expenditure as announced in February 2024, also requires restructuring to align with the reduction in planned capital activities. An S189 consultation process on the restructuring of the Burnstone operations is in progress.

Key Contracts, Suppliers and Consultants
Read, Swatman & Voigt, or RSV (engineering design team for the balance of the engineering design); DLC Town Plan (access surveying and registration of the new servitudes for the new access road to Burnstone); and DTS (appointed for the design change to remove the skips from the shaft using the rock winder bank area).

Contact Details for Project Information
Sibanye-Stillwater executive VP: investor relations James Wellsted, ir@sibanyestillwater.com.

Edited by Creamer Media Reporter

Comments

Showroom

WearCheck
WearCheck

Leading condition monitoring specialists, WearCheck, help boost machinery lifespan and reduce catastrophic component failure through the scientific...

VISIT SHOWROOM 
M and J Mining
M and J Mining

M and J Mining are leading suppliers of physical support systems as used by the underground mining industry. Our selection of products are not...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.117 0.258s - 129pq - 2rq
Subscribe Now