Project Description
The project comprises the Copperwood and Satellite deposits.
The project envisages an estimated 11-year operation averaging payable copper production of 64.6-million pounds a year and payable silver production of 106 966 oz/y.
Life-of-mine production is estimated at 300 000 t of copper and 1.1-million ounces of silver.
Room-and-pillar mining methods will be used given the relatively subhorizontal orebody that varies in thickness from 1.6 m to 3.7 m.
Potential Job Creation
Not stated.
Net Present Value/Internal Rate of Return
The project has an after-tax internal rate of return of 17.6% with a net present value, at an 8% discount rate, of $222-million before taxes and $168-million after taxes. Payback is estimated at 3.5 years.
Capital Expenditure
Initial capital is estimated at $391-million.
Planned Start/End Date
Commissioning and plant ramp-up will take place during the first quarter of 2026.
Latest Developments
Highland Copper has received a nonbinding letter of interest (LoI) from the Export-Import Bank of the United States (Exim) for up to $250-million in potential debt financing to advance its fully permitted Copperwood project.
The LoI, issued under Exim’s Make More in America Initiative and potentially also eligible under its China and Transformational Exports Programme, could support a significant portion of Copperwood’s estimated $400-million initial capital requirement.
Copperwood is among the few copper projects in the US with all major permits secured and a completed feasibility study. Highland is advancing detailed engineering to prepare the project for a construction decision.
Key Contracts, Suppliers and Consultants
GMS (overall report and feasibility study coordination, property description and location, accessibility, history, geological setting and mineralisation, deposit types, exploration, drilling, sample preparation and security, data verification, mineral resource estimates, mineral reserves, mining methods, economic analysis, operating costs, infrastructure, power supply, capital cost estimate and project execution plan); SGS Canada Inc. (Lakefield) (mineral test work; Lycopodium (sheet, mass balance, recovery methods, mineral process plant design and input operating and capital cost estimates for the process plant); Golder Associates (rock mechanics and underground geotechnical assessment, water balance, water treatment design and tailings disposal facility design); and Foth Infrastructure & Environment (environmental, permitting and social aspects).
Contact Details for Project Information
Highland Copper, tel +1 450 677 2455 or email info@highlandcopper.com.
Comments
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation