Fire damage, sanctions delay start of new Russia zinc mine
LONDON - The start of zinc concentrate production at Russia's new Ozernoye mine will be delayed until at least the third quarter of 2024 and a ramp-up to full capacity until 2025, the mine operator said on Monday.
The mine, which was originally due to start production by the end of 2023, was expected to be one of the main drivers of global mine production growth this year, industry association ILZSG said in October.
However, a fire damaged the imported equipment in a part of Ozernoye's plant in November, while U.S. sanctions imposed on the company in December have made it hard to find a replacement abroad, two sources familiar with the matter told Reuters.
"The flotation part of the plant with imported equipment was damaged in the fire. As a result, the technological scheme will be based on flotation equipment that the company has developed by its own design bureau," the company told Reuters.
"The quality of concentrate will not be affected by these changes," it added.
The project, which would be Russia's largest zinc mine, is designed to produce up to 350,000 metric tons of zinc in zinc concentrate. It is already mining ore and stockpiling it until the plant is ready to process it.
Washington's sanctions cemented Ozernoye's dependence on future demand in top consumer China, where the construction sector, a major consumer of steel galvanised with zinc, has had patchy post-pandemic recovery.
Weak demand and the global market surplus, which the ILZSG estimated at 211 000 metric tons in January-November, have pushed zinc prices CMZN3 down 25% over the last 12 months.
Delayed Ozernoye's production will not be able to materially change this picture. Macquarie said that its analysts had updated their estimates to reflect Ozernoye's delay but still expect the global refined zinc market to remain in oversupply this year.
Comments
Press Office
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation