Galena raises A$20m as Abra ramp-up lags

20th April 2023

By: Esmarie Iannucci

Creamer Media Senior Deputy Editor: Australasia

     

Font size: - +

PERTH (miningweekly.com) – Junior Galena Mining on Thursday announced plans to raise A$20-million to provide additional working capital, warning that the ramp-up of its Abra base metals mine, in Western Australia, has been delayed.

“The requirement for additional working capital during ramp-up is disappointing, considering the effort and diligence that everyone involved has put into progressing the mine to this stage,” said MD Tony James.

“The revised geology information affecting the ore that was hard against the Abra fault has been a short-term technical change we did not expect or anticipate. That ore has been replaced by lower-grade ore and we will continue our ramp-up to steady-state production as quickly as possible moving away from the upper northern margin of the orebody.

“The rain in the last week of March hurt us as we have had to slow down work until we re-stock the critical supplies required at the mine. The mine handled the rain well, but the main access roads were hit hard causing extended delays into April.”

As a result of the delay in the ramp-up, and the heavy rains, lead production for the 2023 calendar year is expected to reduce from the previous guidance of between 53 000 t and 68 000 t to between 50 000 t and 60 000 t.

Production unit costs are forecast to increase because of the lower than expected lead production and a 12% increase in overall costs since the last guidance was provided in July 2022. Steady-state life-of-mine guidance continues to show strong financial outcomes following the ramp-up time frame.

“The updated guidance for 2023 also includes some of the cost challenges that everyone in the industry is seeing. Our plan is to push through this ramp-up period as quickly as possible to get into consistent steady-state production,” said James.

To fund additional working capital during the ramp-up of Abra, Galena would place 133.3-million shares, at a price of 15c each, with the company saying on Thursday that it had received binding commitments for the placement.

The company’s largest shareholder, Warburton Group, has subscribed for more than 23.8-million shares worth an estimated A$3.6-million, while debt facilities provider Taurus Mining Finance has subscribed for more than 6.66-million shares worth some A$1-million.

The shares will be issued in two tranches, with the first to raise nearly A$13.9-million under Galena’s existing placement capacity, while the second tranche of 40.4-million shares, raising an additional A$6.1-million, will be subject to shareholder approval at a meeting scheduled for mid-June.

Edited by Creamer Media Reporter

Comments

Showroom

SMS group
SMS group

At SMS group, we have made it our mission to create a carbon-neutral and sustainable metals industry.

VISIT SHOWROOM 
Actom image
Actom

Your one-stop global energy-solution partner

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Photo of Martin Creamer
On-The-Air (15/11/2024)
15th November 2024 By: Martin Creamer
Magazine round up | 15 November 2024
Magazine round up | 15 November 2024
15th November 2024

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.423 0.499s - 149pq - 2rq
Subscribe Now