Lady Julie gold project, Australia

Photo by ©Creamer Media
Name of the Project
Lady Julie gold project.
Location
Eastern Goldfields region of Western Australia.
Project Owner/s
Emerging gold producer Magnetic Resources.
Project Description
A feasibility study has confirmed Lady Julie as one of the highest-margin undeveloped gold projects in Australia.
The operation comprises three openpits – LJN4, Lady Julie Central and Hawkes Nest 9 – an underground mine and a dedicated 2.75-million-tonne-a-year gold processing plant with all associated services and facilities.
Gold production will average 140 000 oz/y over its nine-year mine life when at full production; the plant and facilities will be designed with this timeframe in mind. Life-of-mine production is estimated at 1.02-million ounces.
The project will further require the development of a 20 MW (gas/solar) power station and bore fields for process water.
Potential Job Creation
Not stated.
Net Present Value/Internal Rate of Return
The project has a pretax net present value (NPV), at an 8% discount rate, of A$970-million and an internal rate of return (IRR) of 45%, assuming a gold price of A$4 000/oz.
This increases to an NPV of A$1.67-billion and an IRR of 66% at A$5 145/oz of gold. Payback is estimated at about 30 months.
Capital Expenditure
Initial capital costs are estimated at A$375-million.
Planned Start/End Date
Project construction is expected to take about two years.
Latest Developments
None stated.
Key Contracts, Suppliers and Consultants
Not disclosed.
Contact Details for Project Information
Magnetic Resources, tel +61 89226 1777 or email info@magres.com.au.
Article Enquiry
Email Article
Save Article
To advertise email advertising@creamermedia.co.za or click here
Comments
Press Office
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation