Lance Projects – Ross and Kendrick production areas, US – update


Photo by Peninsula Energy
Name of the Project
Lance Projects – Ross and Kendrick production areas.
Location
Wyoming, US.
Project Owner/s
Independent end-to-end producer of yellowcake Peninsula Energy.
Project Description
The life-of-mine (LoM) plan for the Ross and Kendrick production areas completed in August 2023 delivered a robust and resilient project development plan for Lance, including an accelerated production ramp-up schedule.
The ten-year LoM model is based on a total resource base of 21.8-million pounds of uranium estimated to be contained within the production areas. LoM uranium production is estimated at 14.8-million pounds from the production areas.
The production and LoM plan has been developed for steady-state production of 1.8-million pounds of yellowcake a year from Ross and Kendrick.
The LoM model features a complete 5 000 gallons per minute in situ recovery (ISR) plant to produce up to two-million pounds a year of dry yellowcake product.
The Ross facility, built in 2015 as an alkaline ISR satellite facility, is undergoing an expansion to increase its production capacity from one-million pounds a year to two-million pounds a year. The expansion also aims to add the capability to produce a finished dry yellowcake product, uranium oxide.
Kendrick is the next sequential production area.
The current LoM plan does not include production from Lance’s Barber area, which provides a future expansion opportunity at the project.
Potential Job Creation
Not stated.
Net Present Value/Internal Rate of Return
The project has a net present value, at an 8% discount rate, of $116.2-million and an internal rate of return of 26%.
Capital Expenditure
LoM capital expenditure is estimated at $285.5-million.
Planned Start/End Date
Peninsula is targeting first production of dried yellowcake in the third quarter of 2025.
Latest Developments
Peninsula Energy has terminated five of its six uranium offtake contracts as it advances plans to restart production at the Lance project. The agreements were mutually cancelled, subject to compensation payments totalling $6.6-million.
The company has already paid $1.6-million, with the remaining $5-million to be settled following a capital raise. One contract remains in place, covering deliveries of 100 000 lb/y from 2028 to 2033, under a blended pricing structure combining base and market-linked components.
As of July 27, construction of the central processing plant was complete. Water commissioning, operator training and final regulatory inspections are under way. The plant will enter hot commissioning once it receives standard preoperational approval from the Wyoming uranium recovery programme.
The company has said that on July 10 it secured a $15-million debt facility to support its reset plan. Its shares remain suspended as it finalises production guidance, the capital raise, and associated plans.
Key Contracts, Suppliers and Consultants
Western Water Consultants (definitive feasibility study); and Samuel (detailed engineering and initial long lead time equipment procurement works); and Ross (central processing plant expansion).
Contact Details for Project Information
Peninsula Energy, tel +61 8 6263 4461 or email info@pel.net.au.
Comments
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation