https://newsletter.mw.creamermedia.com
Africa|Construction|Generators|Mining|Power|PROJECT|Resources|Storage|Transformer|Contracting|Transformer
Africa|Construction|Generators|Mining|Power|PROJECT|Resources|Storage|Transformer|Contracting|Transformer
africa|construction|generators|mining|power|project|resources|storage|transformer-company|contracting|transformer

Lindi Jumbo offers opportunity for mining in Tanzania

7th September 2023

By: Esmarie Iannucci

Creamer Media Senior Deputy Editor: Australasia

     

Font size: - +

PERTH (miningweekly.com) – Graphite developer Walkabout Resources is hoping that the development of its Lindi Jumbo graphite mine, in Tanzania, would open the floodgates for foreign investment in the African nation.

Speaking at Paydirt’s Africa Downunder conference, in Perth, Walkabout CEO Andrew Cunningham said on Thursday that the $20-million to $25-million debt funding secured for the development of Lindi Jumbo marked the first foreign debt into the Tanzanian mining industry in the past 20 years, while the project itself was the first major mine to be developed over the last 10 to 15 years.

“Lindi Jumbo really is a game changer for Tanzania, and our hope is that it will help our peers, and help get more foreign debt into Tanzania, and we are hoping that it will open the floodgates,” Cunningham said.

Walkabout on Thursday provided an update on the construction of the Lindi Jumbo project, noting that civil works were more than 97% complete while construction of the tailings storage facility was 90% complete.

The current construction schedule has the connection to the power supply on the Lindi Jumbo critical path. Although grid power has been delivered to site and is awaiting to be energised, the delivery to site of the contracted 33 kV transformer is not expected until November.

To mitigate potential commissioning delays and to reduce future operating risk, Lindi Jumbo had reverted to acquiring diesel generators for full backup power. These generators were expected to arrive on site next month and would be critical for the timely commissioning and startup of the processing plant while the transformer was being installed. The cost of this risk mitigation and redundancy would add nearly $1-million to the project cost and was factored into the sizing of the senior debt facility, the company told shareholders.

Meanwhile, the company told shareholders that the impact of prolongation from the delays in project funding and Covid-19 had been mitigated to approximately 4.2% of the forecasted final capital expenditure value.

Walkabout said on Thursday that with the contracting of the power and camp scope changes and the Lindi Jumbo plant construction nearing completion, the final estimated capital cost for the mine is $34.5-million, up from the $27.8-million estimated in the original definitive feasibility study.

The bulk of this cost was incurred in 2021.

The Lindi Jumbo project would produce 40 000 t/y of graphite over a mine life of 24 years, and Cunningham said the company was hoping to go into commissioning by the end of this year.

Edited by Creamer Media Reporter

Comments

Showroom

AutoX
AutoX

We are dedicated to business excellence and innovation.

VISIT SHOWROOM 
Weir Minerals Africa and Middle East
Weir Minerals Africa and Middle East

Weir Minerals Europe, Middle East and Africa is a global supplier of excellent minerals solutions, including pumps, valves, hydrocyclones,...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Photo of Martin Creamer
On-The-Air (15/11/2024)
15th November 2024 By: Martin Creamer
Magazine round up | 15 November 2024
Magazine round up | 15 November 2024
15th November 2024

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.29 0.377s - 146pq - 2rq
Subscribe Now