Marula highlights Kinusi progress

23rd May 2023

By: Marleny Arnoldi

Deputy Editor Online

     

Font size: - +

 

Tanzania-focused miner Marula Mining says its activities on site at the Kinusi copper project are progressing well, ahead of mining activity, which is planned to start by June 30.

Mining activity will initially comprise small-scale shallow copper mining, as part of Phase 1. 

Marula holds a 75% commercial interest in Kinusi through an agreement with local miner Takela Mining Tanzania, as of April 12.

The company has conducted several successful site visits during May, including mineral processing consultants Southern Metal Processing, which will help finalise plans for the installation of processing plant facilities at Kinusi.

Marula confirms the final design work and detailed costings of this processing plant equipment is ongoing, with visits, inspection and selection of crushing and associated processing units currently under way.

This while additional mining equipment is being sourced in South Africa and is planned to be delivered to the Kinusi site in due course in line with on-site development work.

The company also continues with metallurgical testwork and process optimisation work. Samples have been delivered to SGS Laboratories in Tanzania for assay and metallurgical testing, with results expected by the end of June.  

Marula plans on undertaking, through geological consultants Geofields Tanzania, a diamond drilling programme, comprising holes to depths of 100 m to 150 m.

The drill programme will provide a better understanding of the structural controls to high-grade copper mineralisation and determine the depth expansions of the shallow mineralisation that has been observed.

Marula has also sent sample material from Kinusi to two testing facilities on behalf of four shortlisted global trading community groups, as part of the process to finalise initial offtake terms and conditions.

“We are pleased with the progress that has been made at the Kinusi project. My site visit last week, once again, confirmed the potential that I believe this project holds. Representatives from offtake groups have also conducted site visits, highlighting their interest in the project.

“We are dedicated to creating a project that upholds our commitment to sustainable and responsible practices. We also greatly value the cooperation of the local community, as we continue to implement community-based programmes around the Kinusi mine and region,” says Marula CEO Jason Brewer.

Edited by Chanel de Bruyn
Creamer Media Senior Deputy Editor Online

Comments

Latest News

A test mine established by the MMP
MMP looks to the future with a new strategy
18th November 2024 By: Sabrina Jardim

Showroom

Avlock International
Avlock International

Avlock International is a leading manufacturer and distributor of Specialized Fastening Systems.

VISIT SHOWROOM 
Schauenburg SmartMine IoT
Schauenburg SmartMine IoT

SmartMine IoT has been developed with the mining industry in mind, to provides our customers with powerful business intelligence and data modelling...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Photo of Martin Creamer
On-The-Air (15/11/2024)
15th November 2024 By: Martin Creamer
Magazine round up | 15 November 2024
Magazine round up | 15 November 2024
15th November 2024

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.086 0.165s - 151pq - 2rq
Subscribe Now