https://newsletter.mw.creamermedia.com
Africa|Energy|Financial|Industrial|Power|PROJECT|Projects|Solar|Maintenance
Africa|Energy|Financial|Industrial|Power|PROJECT|Projects|Solar|Maintenance
africa|energy|financial|industrial|power|project|projects|solar|maintenance

Procurement problems

14th October 2022

By: Terence Creamer

Creamer Media Editor

     

Font size: - +

Given the urgency to inject new electricity into South Africa’s load-shedding-prone grid, it is crucial that the procurement rhythm for utility-scale projects be re-established and accelerated.

This rhythm was seriously disrupted in 2015, when the State-captured Eskom leadership at the time refused to sign power purchase agreements with independent power producers on the dubious basis that the utility had returned to a sustained surplus position. That proposition turned out to be false, as delays to the new-build programme combined toxically with maintenance, skills, corruption, industrial relations, and sabotage crises at the old stations to yield an energy shortfall that has made high levels of load-shedding an almost daily reality.

A recent Meridian Economics analysis demonstrates just how damaging that State-captured decision was. It shows that had an additional 5 GW of wind and solar power been built, which is equivalent to the capacity that would have typically been procured over two renewables bidding rounds, 96.5% of the load-shedding implemented in 2021 would have been eliminated.

Addressing the shortfall in the shortest possible time requires not only a massive scaling up in bid-window allocations, but also a streamlining of processes to shorten the time it takes to procure and to ensure that the projects selected are built.

South Africa’s pre-2014 record in this regard was impressive. There has been a marked deterioration, however, since the resumption of procurement under the allocations provided for by the 2019 edition of the Integrated Resource Plan.

The slump started with the so-called risk mitigation programme, which was badly designed from the outset, making life difficult for bidders and the IPP Office alike, with only three of the 11 preferred projects selected having achieved financial close to date.

A recovery was anticipated when the fifth bid window (BW5) of the renewables programme was belatedly launched in 2021, but a combination of delays relating to grid build-out costs and surging energy and project inflation left that process faltering too.

Enter BW6, which was initially expanded from 2 600 MW to 5 200 MW, but later reduced to 4 200 MW after delays to securing the regulator’s concurrence in time to increase the solar allocation from 1 000 MW to 2 000 MW.

While important lessons seem to have been learned from the BW5 difficulties, the late expansion of the round, together with ongoing grid constraints, has meant that only 23 wind bids have been submitted and these have a combined capacity only 30% above the round’s 3 200 MW wind allocation.

The upshot of this lower competition is likely to be higher prices for the first time since the launch of the renewables programme in 2011. However, given the crisis, it would be worse still if the projects were to face commercial trials similar to those that have afflicted most of the aggressively priced BW5 projects.

Fortunately, centralised procurement is no longer the only lever for adding new capacity. Nevertheless, it remains a vital one and has to be pulled if South Africa is to emerge from load-shedding sustainably.

Edited by Terence Creamer
Creamer Media Editor

Comments

Showroom

Flameblock
Flameblock

FlameBlock is a proudly South African company that engineers, manufactures and supplies fire intumescent and retardant products to the fire...

VISIT SHOWROOM 
Yale Lifting Solutions
Yale Lifting Solutions

Yale Lifting Solutions is a leading supplier of lifting and material handling equipment in Southern Africa. Yale offers a wide range of quality...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Photo of Martin Creamer
On-The-Air (15/11/2024)
15th November 2024 By: Martin Creamer
Magazine round up | 15 November 2024
Magazine round up | 15 November 2024
15th November 2024

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.135 0.211s - 127pq - 2rq
Subscribe Now