Semafo hits 97% completion at Boungou, expects first gold by June

17th May 2018

By: Henry Lazenby

Creamer Media Deputy Editor: North America

     

Font size: - +

VANCOUVER (miningweekly.com) – Montreal-based miner Semafo reports that construction of its $231-million Boungou mine, in Burkina Faso, is 97% complete.

Commissioning of the process plant is under way, with the first ore scheduled to be introduced to the mill circuit by month-end, the West Africa-focused miner said on Thursday.

The first gold pour is now pencilled in for June, slightly ahead of schedule.

Semafo said construction of the processing plant is now 100% complete, with commissioning nearing the 60% level.

The crushing circuit, vertimill, pre-leach and tailings thickeners, leaching/carbon-in-pulp circuit and water services are already commissioned and commissioning of the semi-autogenous grinding mill, gravity, elution circuit, gold room, compressors and oxygen plant started earlier this month.

About $202-million of the construction budget has been spent to date.

Further, Semafo said pre-stripping is 87% complete, with 15.6-million of the projected 18-million tonnes extracted. The company has already amassed a stockpile of 70 000 t of low-grade ore on the run-of-mine pad.

Meanwhile, mine operator recruitment and training is nearing the end this month. Eighty-six per cent of the 1 480 personnel, including contractors, have been employed.

The company has now initiated the demobilisation of construction and contract personnel, having worked 515 days without a single lost-time injury.

Edited by Creamer Media Reporter

Comments

Latest News

Magazine round up | 30 May 2025
Magazine round up | 30 May 2025
Updated 2 hours 18 minutes ago By: Creamer Media Reporter

Showroom

Essentra Components
Essentra Components

We are responsible manufacturers of essential components. Manufacturing 80 million parts a week, we have over 1 billion parts in stock.

VISIT SHOWROOM 
Weir
Weir

Weir is a global leader in mining technology. We recognise that our planet’s future depends on the transition to renewable energy, and that...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

An image of Valterra CEO Craig Miller
Valterra Platinum makes its debut on the JSE
28th May 2025 By: Tasneem Bulbulia
Resources Watch
Resources Watch
28th May 2025

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.15 0.225s - 142pq - 2rq
Subscribe Now