Simandou iron-ore project, Guinea – update
Name of the Project
Simandou iron-ore project.
Location
Guinea.
Project Owner/s
Simandou’s mining concession is divided into four blocks.
The project is a partnership between Rio Tinto, Chalco Iron Ore Holdings (CIOH), and a Chinalco-led consortium, Winning Consortium Simandou (WCS), Baowu and the Guinea government.
Simfer Jersey Limited is a joint venture (JV) between the Rio Tinto Group (53%) and CIOH (47%). CIOH is a Chinalco-led JV of leading Chinese State-owned enterprises: Chinalco (75%), Baowu (20%), China Rail Construction Corporation (2.5%) and China Harbour Engineering Company (2.5%).
Simfer is the holder of the mining concession covering Simandou blocks 3 and 4, and is owned by the Guinean State (15%) and Simfer Jersey Limited (85%). Simfer Infraco Guinée will deliver Simfer’s scope of the co-developed rail and port infrastructure, and is a wholly owned subsidiary of Simfer Jersey Limited, but will be co-owned by the Guinean State (15%) after closing of the co-development arrangements.
WCS is a consortium of Singaporean company Winning International Group (50%), Weiqiao Aluminium (50%, part of the China Hongqiao Group) and United Mining Supply Group (nominal shareholding). WCS is the holder of Simandou North blocks 1 and 2 (with the government of Guinea holding a 15% interest in the mining vehicle and WCS holding 85%) and associated infrastructure. Baowu Resources has entered into an agreement to acquire a 49% share of WCS mine and infrastructure projects through a Baowu-led consortium, subject to conditions, including regulatory approvals. In the case of the mine, Baowu has an option to increase its shareholding to 51% during operations.
Project Description
The Simandou project comprises three core elements – a mine, railway and port, as well as associated infrastructure.
The Simfer JV’s mine concession holds an estimated 2.8-billion-tonne mineral resource, of which 1.5-billion tonnes were converted to ore reserves that support a mine life of 26 years, with an average grade of 65.3%.
There will be an openpit iron-ore operation in the Simandou range, in south-eastern Guinea, with an expected peak production of between 95-million and 100-million tonnes a year.
WCS’s blocks 1 and 2 are expected to produce 60-million tonnes a year, and Rio's blocks 3 and 4 about 40-million tonnes a year.
The project includes an estimated 670 km railway to transport the iron-ore from the mine to the Guinean coast and a new deep-water port south of Conakry, on the Morebaya river.
Associated developments to provide utilities and supporting infrastructure for the project include construction facilities, and access to materials, power generation, water, access roads and accommodation.
New infrastructure will become State property upon completion.
Construction of the project will be undertaken in two stages.
During the first stage, the southern Ouelaba mine site will be developed, which will include the construction of the railway and port to a capacity of about 60-million tonnes a year.
The second stage will result in the northern Pic de Fon mine site being brought on line and the capacity of rail and port facilities being expanded, increasing production to between 95-million and 100-million tonnes a year.
The mine will be the biggest integrated mine-and-infrastructure project ever developed in Africa.
Potential Job Creation
It is estimated that the project will create 10 000 direct jobs and more than 100 000 induced jobs, as well as employ more than 3 500 local subcontractors.
Present Value/Internal Rate of Return
Not stated.
Capital Expenditure
Simfer's capital funding requirement for the Simandou project is estimated at $11.6-billion, of which Rio Tinto's share is $6.2-billion.
Planned Start/End Date
First production from the Simfer mine is expected in 2025.
The Simandou project will be completed and put into operation in 2026.
Latest Developments
All conditions have now been satisfied for Rio Tinto’s investment to develop the Simandou project, including the completion of necessary Guinean and Chinese regulatory approvals.
Along with the recent approval by the Simfer board, this allows for Simfer to invest in and fund its share of co-developed rail and port infrastructure being progressed in partnership with WCS, Baowu and the Guinea government.
More than 600 km of new multiuse trans-Guinean railway together with port facilities will allow for the export of up to 120-million tonnes a year of mined iron-ore by Simfer and WCS from their respective Simandou mining concessions.
Under the terms of the transaction, Simfer will acquire a participation in the WCS project companies building rail and port infrastructure, commit to perform a portion of the construction works and commit to funding its share of the overall co-developed infrastructure cost, in an aggregate amount of about $6.5-billion (Rio Tinto: $3.5-billion).
CIOH has now paid its share of capital expenditures incurred or required by Simfer to progress critical works up to completion. A first payment of about $410-million, for expenditures until the end of 2023, was made on June 28, 2024, and a second payment of about $575-million, for 2024 expenditures, was made on July 11, 2024. These amounts settle all expenditures incurred up to date.
The co-developed infrastructure capacity and associated cost will be shared equally between Simfer, which will develop, own and operate a 60-million-tonne-a-year mine in blocks 3 and 4 of the Simandou project, and WCS, which is developing blocks 1 and 2.
Under the co-development arrangement, Simfer and WCS will deliver separate infrastructure scopes to leverage expertise. Simfer will build the 70 km Simfer spur rail line and a 60-million-tonne-a-year transhipment vessel port, while WCS will build the dual track 536 km main rail line, the 16 km WCS spur rail line and a 60-million-tonne-a-year barge port.
Once complete, all co-developed infrastructure and rolling stock will be transferred to and operated by the Compagnie du Transguinéen joint venture, in which Simfer and WCS each hold a 42.5% equity stake and the Guinean government a 15% equity stake.
Key Contracts, Suppliers and Consultants
Fluor (construction contractor); and NRW Holdings (earthworks contract).
Contact Details for Project Information
Rio Tinto, tel +44 20 7781 2000 or email media.enquiries@riotinto.com.
Chalco, tel +86-10 8229 8103.
WCS, tel +224 613 55 55 55 or email info@winningafrica.net.
Comments
Press Office
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation