Name of the Project
Withok tailings storage facility (TSF).

Location
Immediately south of the Brakpan TSF, in Gauteng, South Africa.

Project Owner/s
Gold producer DRDGOLD, a specialist in the recovery of the metal from the retreatment of surface tailings.

Project Description
Withok is DRDGOLD’s longer-term TSF initiative. The TSF will have a deposition capacity of 310-million tonnes and a life of 20 years at an eventual deposition rate of 1.3-million tonnes a month.

Potential Job Creation
Not stated.

Net Present Value/Internal Rate of Return
Not stated.

Capital Expenditure
Not stated.

Planned Start/End Date
DRDGOLD reported in its year-end results in August 2025 that commissioning is expected to start within the next three years.

Latest Developments
DRDGOLD has reported in its results for the six months ended December 31, 2025, that a major milestone during the period has been the appointment by the Department of Water and Sanitation (DWS) of the engineer that DRDGOLD has retained to design and build the Withok TSF as an approved professional person. Only such a person may legally design a TSF and, once the pending environmental authorisation is granted – after all conditions have been met – the engineer’s design will be submitted to the DWS for approval.

A key part of the process is, therefore, ensuring the right team of specialists is in place, while engaging constructively with the DWS to remain aligned with its requirements and progress to licensing as quickly as possible.

DRDGOLD has indicated that delivery on its medium- to long-term plans to reclaim the Marievale and Crown Tailings Complex reserves depends on the success of the Withok project.

Key Contracts, Suppliers and Consultants
Not disclosed.

Contact Details for Project Information
DRDGOLD, tel +27 11 470 2600.
R&A Strategic Communications, Jane Kamau, on behalf of DRDGOLD, email jane@rasc.co.za.

Edited by Creamer Media Reporter

Article Enquiry

Email Article

Save Article

To advertise email advertising@creamermedia.co.za or click here

 

Showroom

Airshrink - CiP
Airshrink - CiP

At Airshrink - CiP, we surpass customer expectations with innovative MV and LV cable accessories, including heat shrink joints, terminations,...

VISIT SHOWROOM 
Werner South Africa Pumps & Equipment (PTY) LTD
Werner South Africa Pumps & Equipment (PTY) LTD

For over 30 years, Werner South Africa Pumps & Equipment (PTY) LTD has been designing, manufacturing, supplying and maintaining specialist...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.324 0.486s - 129pq - 2rq
Subscribe Now