Butcherbird Stage 2 manganese expansion project, Australia

Manganese ore

Photo by ©Creamer Media

18th April 2025

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

     

Font size: - +

Name of the Project
Butcherbird Stage 2 manganese expansion project.

Location
The project comprises eight known manganese mineral resources in an estimated 600 km2 of the southern Pilbara region, in Western Australia.

Project Owner/s
Manganese developer Element 25 (E25).

Project Description
Butcherbird comprises eight known manganese mineral resources.

The project is based on the extraction and processing of the Yanneri Ridge and Coodamudgi mineral resources and reserves. 

It builds on additional resource delineation conducted in June 2024 and an updated mineral resource estimate completed in October 2024, which increased measured and indicated resources at the deposits. 

The project, with an 18.3-year life-of-mine, will use 87% of measured resources and 77% of indicated resources within the Butcherbird resource base. 

The project proposes the expansion of the operation to 1.1-million tonnes a year of manganese concentrate. 

It will use expanded opencut mining methods, a modified primary comminution circuit and a dense-media separation back-end solution to optimise grade and recoveries.

The concentrate production strategy complements and enhances E25’s plan to develop a proposed high-purity manganese sulphate (HPMSM) plant, in Louisiana, in the US, to supply offtake partners General Motors and Stellantis with HPMSM for electric vehicle battery cathodes.

Potential Job Creation
Not stated.

Net Present Value/Internal Rate of Return
The project has a pretax net present value, at an 8% discount rate, of A$561-million and an internal rate of return of 96%, with a payback of 1.3 years.

Capital Expenditure
A$64.8-million, including contingency.

Planned Start/End Date
Expanded mining production and process commissioning are scheduled to start within 14 months from the final investment decision and securing project financing.

Latest Developments
None stated.

Key Contracts, Suppliers and Consultants
Not disclosed.

Contact Details for Project Information
Element25, tel +61 8 6375 2525 or email admin@e25.com.au.
 

Edited by Martin Zhuwakinyu
Creamer Media Senior Deputy Editor

Comments

Showroom

Weir
Weir

Weir is a global leader in mining technology. We recognise that our planet’s future depends on the transition to renewable energy, and that...

VISIT SHOWROOM 
WearCheck
WearCheck

Leading condition monitoring specialists, WearCheck, help boost machinery lifespan and reduce catastrophic component failure through the scientific...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Andrada CEO Anthony Viljoen.
Andrada looking to opening more mines in Namibia
16th April 2025 By: Martin Creamer
Resources Watch
Resources Watch
16th April 2025

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.098 0.243s - 127pq - 2rq
Subscribe Now