Rook 1 uranium project, Canada

Image of yellowcake

Photo by © Bloomberg

21st July 2023

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

     

Font size: - +

Name of the Project
Rook 1 uranium project.

Location
Saskatchewan, Canada.

Project Owner/s
NexGen Energy.

Project Description
Rook 1 is the is the biggest development-stage uranium project in Canada.

The project hosts the Arrow deposit, which, in turn, hosts measured and indicated mineral resources of 256.7-million pounds of uranium contained in 3.75-million tonnes grading 3.1%.

The project has a mine life of 10.7 years, with average production estimated at 28.8-million pounds of uranium in years 1 to 5.

Average life-of-mine production is estimated at 21.7-million pounds a year of uranium.

Access to the underground Arrow deposit will be through two shafts, an 8-m-diameter production shaft (intake air) and a 5.5-m-diameter exhaust shaft (second egress). Access to the workings will be from the production shaft.

Conventional longhole mining will be used for production.

The mining method will use mechanised equipment and conventional processes widely employed in the global mining industry.

The estimated mill capacity is targeted stated at 1 300 t/d of ore.

The key infrastructure contemplated includes:

  • underground infrastructure, including materials handling systems, maintenance facilities, a fuel bay, an explosives magazine, ventilation, a paste backfill and a paste tailings distribution system, electrical and communications facilities, underground water supply and dewatering facilities.
  • an underground tailings management facility.
  • surface support infrastructure for the mine, including headframe and hoist facilities, a surface explosives magazine and ventilation fans.
  • surface support infrastructure for the mill, including a process plant, a solvent-extraction plant, an effluent treatment plant and an acid plant.
  • site support infrastructure, including an accommodation camp, liquefied natural gas (LNG) facilities, an LNG power plant, mine and mill dry facilities, analytical and metallurgical laboratory and maintenance, warehouse and security buildings.
  • a surface ore storage stockpile facility. waste-rock storage facilities for potentially acid-generating, nonpotentially acid-generating and special waste materials.
  • water management facilities, consisting of two site water runoff ponds, six contact water process ponds, a potential acid-generating stockpile runoff collection pond, and conveyance and diversion structures.
  • domestic and/or industrial waste management areas.
  • an airstrip.

Potential Job Creation
Not stated.

Net Present Value/Internal Rate of Return
The project has an after-tax net present value, at an 8% discount rate, of C$3.7-billion and an internal rate of return of 52.4%, with a payback of nine months.

Capital Expenditure
C$1.3-billion.

Planned Start/End Date
Not stated.

Latest Developments
None stated.

Key Contracts, Suppliers and Consultants
None stated.

Contact Details for Project Information
NexGen Energy, tel +1 306 954 2275.

Edited by Martin Zhuwakinyu
Creamer Media Senior Deputy Editor

Comments

Latest News

A test mine established by the MMP
MMP looks to the future with a new strategy
18th November 2024 By: Sabrina Jardim

Showroom

BOVA Safety Wear
BOVA Safety Wear

BOVA cemented their reputation in Africa by delivering high quality engineering through their range of safety footwear. 21 years after producing...

VISIT SHOWROOM 
Condra Cranes
Condra Cranes

ISO-certified Condra manufactures overhead cranes, portal cranes, cantilever cranes and crane components: hoists, drives, end-carriages, brakes and...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Photo of Martin Creamer
On-The-Air (15/11/2024)
15th November 2024 By: Martin Creamer
Magazine round up | 15 November 2024
Magazine round up | 15 November 2024
15th November 2024

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.055 0.196s - 129pq - 2rq
Subscribe Now